"We count on August to get through September and October into November until we're busy again in December," Kathy Weston, owner of Weston Gallery, told NBC10 in late August. She described a business year that peaks in August, slows through the fall and picks back up for the holidays. In 2026, Manasquan's construction schedule runs right across those same months.
The rest of this post traces how that happened, what the borough changed in response, and which downtown dates are still on the calendar before the work stops for the winter.
August, the month that was supposed to carry the fall
The work that started this was underground. The borough has been replacing water, sewer and storm drainage lines beneath the intersection of Main, Broad and South streets. NBC10 reported road closures, detours and fewer parking spaces along Main Street. The utility project was expected to finish by the end of September. Weston said her section of Main Street was closed to traffic and her late-summer sales were down about 30%.
Merchants filled the council meeting on Aug. 17. Jennifer Burger, owner of Main Street Gallery, said the work had cut her business by about 70%. John Newman, owner of Bouquets to Remember and a former Chamber of Commerce president, said: "People can't park. They can't conveniently walk in." Another speaker that night explained the timing problem: "a disruption in August is a disruption for September, October, and November."
The Chamber made a specific request. Alison Manser Ertl, publisher of The Coast Star and the Chamber's vice president, read a statement asking for a holiday construction pause between Thanksgiving and Christmas.
What the holiday request actually got
The answer came back narrower than the request. After talks with county officials, Mayor Mike Mangan and the council paused the Monmouth County roundabout at Main, Broad and South streets for the fall and holiday season. Construction there had been expected to start in November or December. It is now scheduled for spring 2027. The mayor also said utility pole relocation could still happen this fall, and its timing and impact are unknown. If you saw NBC10's August report saying the county project would begin in November, that timeline has since been replaced.
Main Street did not get a full pause. A separate project, Streetscape Segment D, started Sept. 21. It covers "Main Street from Exxon to Train Station; Route 71 limits." The borough's schedule on squanprojects.com, labeled as of Oct. 1, 2026, gives Segment D a construction window of Sept. 21 to Dec. 15, 2026, followed by a seasonal shutdown and another construction period. TAPinto's Sept. 23 report said to expect variable lane shifts and sidewalk closures through December, with crews returning in the spring to finish.
Put the pieces side by side and the holiday season looks like this:
| Project | Where | Fall 2026 status |
|---|---|---|
| Underground utility work | Main, Broad and South streets intersection | Expected to finish by end of September |
| Streetscape Segment D | Main Street from Exxon to the train station, Route 71 limits | Construction Sept. 21 to Dec. 15, then seasonal shutdown |
| County roundabout | Main, Broad and South streets | Moved to spring 2027; utility pole relocation possible this fall |
| Streetscape Segments A and C | Atlantic Avenue to South Street Plaza; Joe Leone's to Exxon | Construction March 1 to May 31, 2027 |
If the schedule holds, crews leave Segment D in mid-December. That leaves the final stretch before Christmas without a scheduled streetscape crew, while most of November still sits inside the Segment D window. Spring 2027 is where several projects are now stacked: the roundabout, Segments A and C, and the return to finish Segment D.
Elsewhere in town, milling and paving along 1st Avenue and Riverside Drive is finishing a project that began in the spring. The borough's notice lists parking restrictions there, separate from the Main Street work.
The first new fall event isn't on Main Street
The season's newest event is about a block off the corridor. The inaugural Manasquan Market runs Saturday, Oct. 3, from 9 a.m. to 1 p.m. in the parking lot of the Manasquan Senior Community Center, 63 Atlantic Ave. The Manasquan Chamber of Commerce is presenting it with Two River Dairy. Organizers list farm-fresh produce, local foods, baked goods, artisan products, and plants and flowers. The market is rain or shine. The Chamber's calendar shows only the Oct. 3 date, and no recurring schedule has been announced.
The Saturday, Oct. 24 event is harder to pin down. The Chamber's calendar lists a Fall Craft Fair from 10 a.m. to 4 p.m. The Coast Star's August fall roundup listed the same hours as the Fall Squan Artisan Market on Main Street. Other event listings call it Squantoberfest and place it at Squan Plaza or on Abe Voorhees Drive. No Chamber or borough notice says the event has moved, so check the Chamber's page for the final location before you go.
The November dates inside the construction window
Two Chamber dates fall while Segment D is scheduled to be active:
- Ladies Night, Thursday, Nov. 19, 4 to 8 p.m.
- Pink Friday, Friday, Nov. 20, 10 a.m. to 5 p.m.
These are the first downtown shopping nights of the holiday season. They land about four weeks before the scheduled end of Segment D's fall work.
Two Main Street addresses that opened this year are part of that downtown mix. Lenny's Colonial Ranch Meat Market opened its second storefront at 149 Main St. on March 1. It shares the address with Mueller's Bakery, Batch on Main and Shore Fresh Seafood. Coastal Canteen, a coastal-tavern restaurant with rooftop seating, opened at 142 Main St. on May 20.
What the borough is building beyond the pavement
Borough hall has also started working on how it deals with downtown businesses, and these proposals will shape future fall calendars.
The first is a relief effort. On Sept. 1, the council mailed a Main Street construction impact survey to affected businesses. It asks owners to estimate profits lost or gained in August 2026 compared with August 2025. The form says no funding program exists yet, submitting it does not guarantee payment, and any estimates would need to be verified with financial records. Mangan called the streetscape "a once-in-a-generation upgrade to the most important part of our community, other than the beach," and said the goal is "to make everybody whole."
The second is a business registry. Borough officials have said not having a list of businesses made direct communication difficult. The ordinance is set for introduction at the Oct. 5 council meeting. Businesses already operating on or before March 31, 2027 would not pay to register, and there would be no fee in the first year.
The third is a proposed Business Improvement District, which would give Main Street businesses a direct role in the kind of events this post covers. The proposed district would include Main Street and surrounding blocks, an area with 83 businesses the borough surveyed this summer. A one-shop storefront would pay $29 a month, or $350 a year. The borough would add $30,000 a year, for an estimated annual budget of about $58,000. An 11-member board would hold seven seats for Main Street business owners and operators. The budget could cover a coordinator plus banners, planters, seasonal decorations and small repairs. The council expects to introduce and adopt the ordinance in October or November. An interim board would be appointed in November and serve until a first election proposed for August 2027. Gateway signs and a trolley are still being developed. Parking changes, bike lanes and a parking garage are on hold.
If the BID is adopted on that schedule, its first board would be in place while Segment D is still scheduled to be active.